Project Experience
![Landscape, mountains](https://www.krakataueng.co.id/assets/images/project/827/1.jpg)
RELOCATION TOWER 150KV CONCENTRATOR 130 AMMAN MINERAL
Client | : | AMMAN MINERAL NUSA TENGGARA |
Location | : | SUMBAWA, NTB - Indonesia |
Period | : | 2022 |
Outline of Project
EPC PROJECT TOWER
Scope of Work
Procurement and Construction
![Landscape, mountains](https://www.krakataueng.co.id/assets/images/project/325/1.jpg)
PACKAGE 12-073 (EPC COAL HANDLING FACILITY MTBU-B PHASE-5 & CRUSHING PLAN -TAL, CHF-SP-2 TANJUNG ENIM) PT. BUKIT ASAM
Client | : | PT. BUKIT ASAM |
Location | : | TANJUNG ENIM - SUMATERA SELATAN |
Period | : | 2014 |
Outline of Project
Coal Handling Facility Project consist establihment of Conveyor System for coal transport
![Landscape, mountains](https://www.krakataueng.co.id/assets/images/project/66/1.jpg)
TARAHAN PORT EXPANSION PHASE-5 (PACKAGE 10-183)
Client | : | PT.BUKIT ASAM |
Location | : | LAMPUNG |
Period | : | 2014 |
Outline of Project
Increasing of coal handling facilities and Tarahan port expansion phase 5 ( package 10-183 )
Scope of Work
Engineering, Procurement, Contruction
![Landscape, mountains](https://www.krakataueng.co.id/assets/images/project/304/14707-gambar_2.jpg)
PENYAMBUNGAN KONSUMEN TEGANGAN TINGI PT. CEMINDO GEMILANG, PAKET 1 : PENGADAAN & PEMASANGAN SUTT 150 kV GI PELABUHAN RATU - GI BAYAH
Client | : | PT. PLN (Persero) UIP Transmisi Interkoneksi Sumatera Jawa |
Location | : | Pelabuhan Ratu |
Period | : | 2013 |
Outline of Project
Overhead HVDC Transmission Line System 150 KV
![Landscape, mountains](https://www.krakataueng.co.id/assets/images/project/289/14705-gambar_2.jpg)
PEKERJAAN PENGADAAN PEMASANGAN JARINGAN INTERKONEKSI 150 kV BATAM - BINTAN PAKET 2 : TRANSMISI DAN GARDU INDUK 150 kV
Client | : | PT. PLN UIP JARINGAN SUMATERA I |
Location | : | Batam - Bintan |
Period | : | 2013 |
Outline of Project
Overhead HVDC Transmission Line System & Transformer 150 KV
![Landscape, mountains](https://www.krakataueng.co.id/assets/images/project/44/1.jpg)
COMBINED CYCLE POWER PLANT (CAPACITY 120 MW)/ OWNER SCOPE PROYEK COMBINED CYCLE POWER PLANT (CAPACITY 120 MW)
Client | : | PT KRAKATAU DAYA LISTRIK |
Period | : | 2012 |
Outline of Project
Build a New 120MW Combined Cycle Power Plant
Scope of Work
Procurement and Construction
![Landscape, mountains](https://www.krakataueng.co.id/assets/images/project/430/1.jpg)
NEW GATHERING STATION AT NIRU STRUCTURE
Client | : | PT. Pertamina EP |
Location | : | Niru - South Sumatra |
Period | : | 2011 |
Outline of Project
Construction the niru gathering station facility to handle oil production from 27 well and 2 injection wells at niru area. The capacity of each well is predicted around 850 BFPD, total fluida is amount 23.000 BFPD
Scope of Work
Procurement and Construction
![Landscape, mountains](https://www.krakataueng.co.id/assets/images/project/417/1.jpg)
BARGE LOADING FACILITY EXTENSION KPC
Client | : | PT Kaltim Prima Coal |
Location | : | Sangata, East Kalimantan |
Period | : | 2011 |
Scope of Work
Engineering, Procurement and Construction
![Landscape, mountains](https://www.krakataueng.co.id/assets/images/project/415/1.jpg)
CONSTRUCTION OF JETT Y FOR CONTINOUS BARGER UNLOADER AT NORTH COAL TERMINAL
Client | : | PT Nusa T ambang Pratama |
Location | : | Pulau Laut, Kotabaru - South Kalimantan |
Period | : | 2011 |
Outline of Project
Capacity Enhacement of Jetty and Conveyor for Coal Handling Services
Scope of Work
Engineering, Procurement and Construction
![Landscape, mountains](https://www.krakataueng.co.id/assets/images/project/413/1.jpg)
ASAM-ASAM CPP AND OLC PROJECT
Client | : | PT Nusa Tambang Pratama |
Location | : | Kalimantan Selatan - Indonesia |
Period | : | 2011 |
Outline of Project
Capacity Enchancement of Coal Conveyor & Jetty Handling
Scope of Work
Engineering, Procurement, Construction